Câu 131: Project Management Professional (PMBOK 6 and 7)

A project team with members from many different countries is struggling to cooperate. The project manager accepted these difficulties during the storming phase of team development, but the team has not moved to the next phase. The project is beginning to fall behind schedule. What can the project manager do to move th…

Nội dung câu hỏi

A project team with members from many different countries is struggling to cooperate. The project manager accepted these difficulties during the storming phase of team development, but the team has not moved to the next phase. The project is beginning to fall behind schedule. What can the project manager do to move the team to the norming phase?

Các lựa chọn

Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.

  1. A. Plan social activities to help foster stronger interpersonal relationships and identify shared goals. — đáp án hiện tại
  2. B. Figure out who is behind the issues and apply progressive disciplinary techniques.
  3. C. Speak with the project sponsor about changing the team composition.
  4. D. Show the team the schedule impact of their communication issues and encourage them to put their differences aside.