Câu 195: Project Management Professional (PMBOK 8)
A construction project is in its final stage when the owner of a private property where the pipeline is routed refuses to collaborate. The lack of collaboration causes a project delay, but the client insists that the project must be completed as per the contract. What should the project manager do next?
Nội dung câu hỏi
A construction project is in its final stage when the owner of a private property where the pipeline is routed refuses to collaborate. The lack of collaboration causes a project delay, but the client insists that the project must be completed as per the contract. What should the project manager do next?
Các lựa chọn
Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.
- A. Request additional budget from the project sponsor and raise a dispute with the property owner to force them to collaborate.
- B. Escalate the routing pipeline issue to the project change control board (CCB) and wait for a resolution to the conflict.
- C. Use the contingency reserve, add more resources, and reroute the pipeline to complete the project as per the contract time line.
- D. Review the agreement with the property owner, schedule a meeting with them to discuss their concerns, and inform the client. — đáp án hiện tại