At the postevent review of an annual conference, the project manager realizes that the team could benefit from improvements in how they handle sponsorship agreements and event logistics. Specifically, the team found that having clearer contracts with sponsors earlier in the planning process would help avoid last-minut…
Nội dung câu hỏi
At the postevent review of an annual conference, the project manager realizes that the team could benefit from improvements in how they handle sponsorship agreements and event logistics. Specifically, the team found that having clearer contracts with sponsors earlier in the planning process would help avoid last-minute issues. How should the project manager handle the organizational process assets (OPAs)?
Các lựa chọn
Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.
- A. Wait until the next event is completed before updating the OPAs so the recommendations are validated before documenting.
- B. Update the OPAs with the recommendations based on the current project evaluation of the sponsor contract process. — đáp án hiện tại
- C. Align the OPAs with general event management guidelines based on industry good practices.
- D. Focus on updating the OPAs with feedback from attendees about the sponsor contract process.