In the last project status meeting, a team member reported some tasks with conflicting priorities. Now, other team members are delayed in their tasks due to the dependencies. What should the project manager do to address this situation?
Nội dung câu hỏi
In the last project status meeting, a team member reported some tasks with conflicting priorities. Now, other team members are delayed in their tasks due to the dependencies. What should the project manager do to address this situation?
Các lựa chọn
Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.
- A. Create a change request and update the project schedule.
- B. Work with the team members to balance the workload. — đáp án hiện tại
- C. Escalate the issue with the team member to their functional manager.
- D. Analyze the critical path and request additional resources.