Câu 106: Project Management Professional (PMBOK 8)

A project manager is working on a project. A few months after the project has launched, the project manager starts receiving complaints from the business unit managers about the lack of updated project information. What should the project manager do?

Nội dung câu hỏi

A project manager is working on a project. A few months after the project has launched, the project manager starts receiving complaints from the business unit managers about the lack of updated project information. What should the project manager do?

Các lựa chọn

Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.

  1. A. Review the communications management plan and stakeholder register. — đáp án hiện tại
  2. B. Run Monte Carlo simulation to identify any flaws in the communication matrix.
  3. C. Request that the business unit managers attend weekly review meetings.
  4. D. Check the organizational responsibility of functional managers in the project.