A project manager uses a laissez-faire leadership style with a newly hired project team. The project manager quickly notices that team members are underperforming, the schedule is delayed, and the project is overbudget. What should the project manager have done at the start of the project?

Nội dung câu hỏi

A project manager uses a laissez-faire leadership style with a newly hired project team. The project manager quickly notices that team members are underperforming, the schedule is delayed, and the project is overbudget. What should the project manager have done at the start of the project?

Các lựa chọn

Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.

  1. A. Managed the team as necessary and allowed them to work on their own
  2. B. Adapted a direct management style according to the project team's needs — đáp án hiện tại
  3. C. Established goals and provided the project team with sufficient authority to work
  4. D. Adapted a servant leader management style to support the team's development