Câu 121: Project Management Professional (PMBOK 8)

A project manager is assigned to a new project to deliver a product at the end of the year. The project manager was informed by the vendor that a core component could not be shipped on time, which will impact the schedule. What should project manager to do next to minimize the impact on the project?

Nội dung câu hỏi

A project manager is assigned to a new project to deliver a product at the end of the year. The project manager was informed by the vendor that a core component could not be shipped on time, which will impact the schedule. What should project manager to do next to minimize the impact on the project?

Các lựa chọn

Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.

  1. A. Schedule a meeting with all stakeholders to extend the project deadline
  2. B. Replace the vendor with a new vendor who can offer the component on time
  3. C. Add an item to the next status review to make stakeholders aware of the vendor issue
  4. D. Review and update the issue log and determine if any alternative components can be offered — đáp án hiện tại