CertyRush
Đang tải...
C CertyRush
Câu hỏi free preview

Câu 122: Project Management Professional (PMBOK 8)

A project is in midway and a time-sensitive initiative was approved but it was later found there was no remaining authorized budget in the project. A new project manager was brought in at the execution phase. What should the project manager do first?

Nội dung câu hỏi

A project is in midway and a time-sensitive initiative was approved but it was later found there was no remaining authorized budget in the project. A new project manager was brought in at the execution phase. What should the project manager do first?

Các lựa chọn

Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.

  1. A. Calculate the budget needed to complete the remaining tasks in the project and include ample contingency reserves.
  2. B. Talk to leadership to stop the project until all needed funds are secured.
  3. C. Review the project's current expenses and advise what risks may arise.
  4. D. Evaluate the current cost performance to determine the required budget for completing the future tasks and risks. — đáp án hiện tại

Cộng đồng

0 bình luận công khai. Tên thành viên được ẩn một phần.

Chưa có bình luận. Mở giao diện tương tác để bắt đầu thảo luận.

Câu hỏi liền kề