Câu 92: Project Management Professional (PMBOK 8)
A product owner who possesses a strong technical background has been actively involved with the project team for several years. The product owner has been quite vocal about the expected duration of the work. As a result, the project team has ceased providing development estimates to avoid causing any dissatisfaction w…
Nội dung câu hỏi
A product owner who possesses a strong technical background has been actively involved with the project team for several years. The product owner has been quite vocal about the expected duration of the work. As a result, the project team has ceased providing development estimates to avoid causing any dissatisfaction with the product owner. What should the project manager do?
Các lựa chọn
Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.
- A. Facilitate the meetings and ask the project team for the estimates.
- B. Conduct a meeting with the project team and the product owner to reset the ground rules for providing estimates. — đáp án hiện tại
- C. Ask the project team to send the estimates via email and not to discuss them during planning meetings.
- D. Meet with the product owner and project team separately to find a compromise.