Câu 93: Project Management Professional (PMBOK 8)
A project manager is assigned to lead a team comprised of business executives. After several roadmaps were denied by the sponsor, the project manager asks to be removed from the project. The sponsor urges the project manager to find a solution as the sponsoring organization has requested their assignment. What should…
Nội dung câu hỏi
A project manager is assigned to lead a team comprised of business executives. After several roadmaps were denied by the sponsor, the project manager asks to be removed from the project. The sponsor urges the project manager to find a solution as the sponsoring organization has requested their assignment. What should the project manager do?
Các lựa chọn
Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.
- A. Schedule deliverables solely based on priorities and must-have-by dates, and gauge the responses.
- B. Hold a team meeting emphasizing existing governance policies and procedures.
- C. Adopt a project framework aligned to the executive's availabilities and then evaluate the risks. — đáp án hiện tại
- D. Speak with the executives to emphasize that the project manager was specifically requested for this project.