Câu 46: PRINCE2 Practitioner Edition 6
MANAGING PRODUCT DELIVERY -Stage 2 is in progress. While producing the team plan, the team manager responsible for the work package to develop the 'classroom-based training material' discovered that the representatives assigned to check the products were unsuitable. Which action should the team manager take in respons…
Nội dung câu hỏi
MANAGING PRODUCT DELIVERY -Stage 2 is in progress. While producing the team plan, the team manager responsible for the work package to develop the 'classroom-based training material' discovered that the representatives assigned to check the products were unsuitable. Which action should the team manager take in response?
Các lựa chọn
Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.
- A. Discuss the situation with project assurance.
- B. Advise the project manager of this risk. — đáp án hiện tại
- C. Update the quality register with these concerns.
- D. Raise an exception report to the project manager.