Câu 45: PRINCE2 Practitioner Edition 6
While producing the Team Plan to deliver the agreed Work Package, it became apparent that the user representatives assigned 10 check some of the products were unsuitable. Which 2 actions should the Team Manager take in response to this situation?
Nội dung câu hỏi
While producing the Team Plan to deliver the agreed Work Package, it became apparent that the user representatives assigned 10 check some of the products were unsuitable. Which 2 actions should the Team Manager take in response to this situation?
Các lựa chọn
Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.
- A. Consult the Senior Supplier to assign suitable reviewers. — đáp án hiện tại
- B. Discuss the situation with Project Assurance and agree the changes or additions to the reviewers. Advise the Project Manager of this risk. — đáp án hiện tại
- C. Ensure the Quality Register is updated with details of the agreed amendments to the reviewers.
- D. Notify the Project Manager by raising an Exception Report explaining that the original reviewers are unsuitable.