Câu 49: PRINCE2 Practitioner Edition 6
The project board has asked user and supplier assurance to review all product descriptions relating to the 'updated corporate quality procedures', prior to authorizing the stage plan for stage 3. Is this appropriate as part of the 'directing a project' process, and why?
Nội dung câu hỏi
The project board has asked user and supplier assurance to review all product descriptions relating to the 'updated corporate quality procedures', prior to authorizing the stage plan for stage 3. Is this appropriate as part of the 'directing a project' process, and why?
Các lựa chọn
Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.
- A. Yes, because project assurance should assess whether all stakeholders have been identified, if requested by the project board.
- B. Yes, because project assurance should review the stage 3 plan for viability, if requested by the project board.
- C. No, because the project manager is responsible for writing product descriptions when creating the stage 3 plan.
- D. No, because the project board should review new product descriptions before they authorize the stage 3 plan. — đáp án hiện tại