Câu 50: PRINCE2 Practitioner Edition 6
During stage 3, the team manager reports that the work to update the 'corporate quality procedures' has been completed and the product is ready to be delivered. What should project assurance do next?
Nội dung câu hỏi
During stage 3, the team manager reports that the work to update the 'corporate quality procedures' has been completed and the product is ready to be delivered. What should project assurance do next?
Các lựa chọn
Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.
- A. Update the team plan to show that the work package is complete.
- B. Check the work package and follow the procedure to deliver completed products.
- C. Verify that all the products to be delivered by the work package are approved. — đáp án hiện tại
- D. Update the stage plan to show the work package as completed.