Câu 90: PRINCE2 Practitioner Edition 6
There is no project schedule in the Project Initiation Documentation. How can project progress be tracked without a schedule to track against?
Nội dung câu hỏi
There is no project schedule in the Project Initiation Documentation. How can project progress be tracked without a schedule to track against?
Các lựa chọn
Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.
- A. This is an error as a Gantt chart or some form of time line, where actuals will be recorded and tracked against the planned schedule of delivery, is mandatory.
- B. Progress can be recorded and tracked using the product checklist, with the planned and actual quality management activities captured in the Daily Log. — đáp án hiện tại
- C. With a clear end date of 30 November, and a small number of Work Packages, the Project Board should track project progress using individual Team Plans.