Câu 90: PRINCE2 Practitioner Edition 6

There is no project schedule in the Project Initiation Documentation. How can project progress be tracked without a schedule to track against?

Nội dung câu hỏi

There is no project schedule in the Project Initiation Documentation. How can project progress be tracked without a schedule to track against?

Các lựa chọn

Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.

  1. A. This is an error as a Gantt chart or some form of time line, where actuals will be recorded and tracked against the planned schedule of delivery, is mandatory.
  2. B. Progress can be recorded and tracked using the product checklist, with the planned and actual quality management activities captured in the Daily Log. — đáp án hiện tại
  3. C. With a clear end date of 30 November, and a small number of Work Packages, the Project Board should track project progress using individual Team Plans.