The change control approach defines how products should be controlled and protected during the project. The accreditation of the 'classroom-based training materials' was planned to take place during stage 2. At the end of the stage, the configuration item record shows that the 'classroom-based training materials' have…
Nội dung câu hỏi
The change control approach defines how products should be controlled and protected during the project. The accreditation of the 'classroom-based training materials' was planned to take place during stage 2. At the end of the stage, the configuration item record shows that the 'classroom-based training materials' have been accredited. However, the project manager decides to request an audit of the product as well. Is this appropriate, and why?
Các lựa chọn
Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.
- A. Yes, because the project should verify that the recorded status reflects the actual status of the products. — đáp án hiện tại
- B. Yes, because the change control approach should specify how the configuration item records are approved.
- C. No, because the project manager should ensure that the change control approach is tailored to the project.
- D. No, because the issue management and change control procedures can be treated as separate, but related, procedures.