CLOSING A PROJECT -The Health and Safety Training Project is part of a strategic program for ABC. The updated benefits management approach needs to be checked when the products are being handed over. This check should ensure that it includes appropriate activities to assess whether the actual course sales meet the agr…

Nội dung câu hỏi

CLOSING A PROJECT -The Health and Safety Training Project is part of a strategic program for ABC. The updated benefits management approach needs to be checked when the products are being handed over. This check should ensure that it includes appropriate activities to assess whether the actual course sales meet the agreed forecast in the business case. Which role should undertake this review as part of the 'closing a project' process?

Các lựa chọn

Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.

  1. A. Program management.
  2. B. Project board.
  3. C. Project manager.
  4. D. Project assurance. — đáp án hiện tại