Câu 41: PRINCE2 Practitioner Edition 6
The project is now in stage 2. The Project Manager has heard about the possibility of a competitor also producing a calendar to be delivered earlier than the target date for this project. There is a threat that the early release of a competitor's calendar may weaken the impact of the MNO Manufacturing Company calendar…
Nội dung câu hỏi
The project is now in stage 2. The Project Manager has heard about the possibility of a competitor also producing a calendar to be delivered earlier than the target date for this project. There is a threat that the early release of a competitor's calendar may weaken the impact of the MNO Manufacturing Company calendar, thereby reducing the anticipated benefits of the Calendar project. Which 2 statements should be recorded under the Roles and responsibilities heading?
Các lựa chọn
Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.
- A. Each risk will be assigned a risk owner.
- B. Risks exceeding the agreed project risk tolerance will be reported to the Project Board. — đáp án hiện tại
- C. Risk tolerances are allocated to each stage by the Project Manager.
- D. Project Assurance will ensure that project risks are identified, assessed and controlled according to the agreed risk management procedure. — đáp án hiện tại
- E. An external consultant is to facilitate a risk identification workshop.