Câu 111: PRINCE2 Practitioner Edition 6

During the initiation stage, the project manager aligns the project's risk management approach to ABC Company's risk management policy. As a result, the project will use two risk registers, one for ABC Company's risks and one for external supplier risks. Is this an appropriate application of the 'tailor to suit the pr…

Nội dung câu hỏi

During the initiation stage, the project manager aligns the project's risk management approach to ABC Company's risk management policy. As a result, the project will use two risk registers, one for ABC Company's risks and one for external supplier risks. Is this an appropriate application of the 'tailor to suit the project' principle, and why?

Các lựa chọn

Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.

  1. A. Yes, because the risk management approach should comply with the supplier's needs.
  2. B. Yes, because project controls should take the project's environment into account. — đáp án hiện tại
  3. C. No, because all three stakeholder interests need to be represented effectively on the project.
  4. D. No, because a single risk register should be used to record risks to the project.