CertyRush
Đang tải...
C CertyRush
Câu hỏi free preview

Câu 112: PRINCE2 Practitioner Edition 6

The quality review of the 'training venue specifications' reported that no quality criteria had been decided for the geographical location of the venues. In a previous project, there was low attendance at the training events because delegates were required to travel a long distance, which caused a risk to the project.…

Nội dung câu hỏi

The quality review of the 'training venue specifications' reported that no quality criteria had been decided for the geographical location of the venues. In a previous project, there was low attendance at the training events because delegates were required to travel a long distance, which caused a risk to the project. Therefore, the executive is concerned if project risk processes are being followed and has asked project assurance to audit the application of the Health and Safety TrainingProject's risk -management approach. Is this an appropriate application of the 'risk' theme, and why?

Các lựa chọn

Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.

  1. A. Yes, because the identified risk is critical to the successful delivery of the pilot courses — đáp án hiện tại
  2. B. Yes, because a review that the risk management approach has been property implemented is required
  3. C. No, because reviewing the implementation of the risk management approach will not mitigate the identified risk
  4. D. No, because a review of processes should be earned out by resources external to the project

Cộng đồng

0 bình luận công khai. Tên thành viên được ẩn một phần.

Chưa có bình luận. Mở giao diện tương tác để bắt đầu thảo luận.

Câu hỏi liền kề